Wembley's owners are confident the rebuilt stadium will be open for business by the end of the year but believe builders Multiplex will miss their September deadline.
Work remains to be done on seating, drainage, the roof and building management systems. And as the project nears completion Wembley National Stadium Ltd (WNSL) will take matters into their own hands and have confirmed their view of how long the final stages of construction will take.
WNSL chief executive Michael Cunnah issued a statement, saying: "Currently Multiplex states that it will complete the stadium by September 2006. It is WNSL's view that, at the current rate of progress, particularly in light of the extensive testing and commissioning regime that will be required, this is not likely to be achieved until later in the year."