Wembley crisis takes new twist

1 april 2006, 13:15

The Wembley Stadium debacle is heading for the law courts after the builders' refusal to pay penalty clauses for yet another delay to the 757million project.

Multiplex should have stumped up 140,000-a-day for every day beyond a January 31 deadline but claim they should be allowed until the end of September due to changes in the contract.

Wembley chief executive Michael Cunnah said: "The financial issues between ourselves and Multiplex are just that, between us and Multiplex, and we have a fixed-price contract that we are very happy to rely upon. We would reject any claims from Multiplex to the contrary."